While scheduling a business process in Сontrol Tower we will have “Schedule Period” and “Schedule Frequency”. Can someone please elaborate what is the difference/connection between them?

1 Like

Hi @YadavYadu

Schedule period is the period of time, during which the process should be triggered.
Schedule frequency defines how often is it triggered.

For example, Schedule period can be set to “April 17, 2019 - June 30, 2019”; and Schedule frequency can be set to “9 am on Monday”. It will mean that the BP will be triggered each Monday at 9 am till June 30, 2019, and after that date it will no longer be triggered.

You can read more about the Schedule here
https://kb.workfusion.com/display/RPAe/How+to+Schedule+a+Business+Process

2 Likes

And both “Schedule Period” and “Schedule Frequency” will be in GMT right?

Yes, correct.